ADP
SR |
Name of Scheme / Market |
Scope of Physical Works |
Achievements |
| 42 |
Development of Internal Road Water supplydrainage and other modern facilities and liblities of KESC in sabzi Mandi Karachi
|
| Constn. of int. sewerage line and 3000 rft External nala |
96% work Completed |
| Constn. of C.C. Road. |
40% work completed |
| Laying of 36" dia AXTC pipe for main disposal. |
Completed |
| Constn. of heavy rain pump 12*12 motor.house |
40% work completed |
| Open rain lock (pen stock gate) |
5% work completed |
| P/L J.testing 8" dia MS pipe line |
95 % work completed |
| P/L J.testing 3" dia GL pipe line WS |
94% work completed |
| Re-constt: of foot paths |
90% work completed |
| P/F Electric mask light |
Completed |
| Constn. og open drain lock from side |
10% work completed |
| 12" & 9" internal sewerage line |
98% work completed |
|
| 43 |
Establishment of meat, Fish and Vegetable Market at Qasimabad, Hyderabad under PPP (Boundary wall) |
| Main Building |
|
| Constt: of Boundary wall |
Compound wall work started, but held up due to dispute over plot |
| internal roads |
|
Water supply and sewerage line underground tank
|
|
| Modern facilities |
|
| Ext. Dev. |
|
| Energization |
|
| Suigas |
|
| |
|
|
| 44 |
Establishment new Subzi Mandi/Cold storage at karachi (2 Nos), Mirpurkhas, Tando Allahyar and Shahpur jahania.
New Sabzi Mandi Northern Bye-Pass, Karachi |
1/-Nothern By Pass
|
|
| Compound wall |
Front & left side c/wall s/Strctr Col.in prog. |
| Int' Road |
Tender under Process |
| Water supply. |
Tender under Process |
| Drainage & other Modern Facilities & Libilities of KESC. |
Tender under Process |
| U.G Tank |
Completed |
| |
|
|
| |
New Sabzi Mandi Ghaghar Pathak, Karachi |
| 2/-Ghaghar Pathak |
Black masonary above pilnth in prog |
| Compound wall |
in progress |
| Int'l Road |
Tender under Process |
| Water supply. |
Tender under Process |
| Drainage & other Modern Facilities & Libilities of KESC. |
Tender under Process |
| U.G Tank 2 lacs gallon |
Completed |
| |
|
|
| |
Cold Storage Mirpurkhas. |
| Cold storage in Existing Godown |
Reno. Work in Progress |
| Plate Form |
Finishing in Progress |
| C/Wall |
|
| Main Gate 2 Nos. |
|
| Internal Road / Earth Filling |
Completed |
| Freezing plant |
Work in Progress. |
| Ext. Electric Services |
--- |
| D.Note for WAPDA |
Transformer Purchase |
| Open Surface drain |
--- |
| |
|
|
| |
Cold Storage Tando Allahyar |
| Godown / Storages |
Finishing in Progress. |
| Plat Form |
|
| Constt: of Internal roads. |
Work in Progress |
| Earth filling |
Work in Progress |
| U/G tank (20000 gl) / HSR (10000) |
Work in Progress |
| Ext. Electric Services |
Work in Progress |
| Freezing Plant |
Work in Progress |
| D.Note for WAPDA |
Paid |
| Pump room / open surface drain |
--- |
| |
|
|
| |
Cold Storage Shahpur Jehanya |
| Estt: of cold storages (Main bldgs) |
Finishing in Progress. |
| Compound Wall |
Completed |
| Constt: of Main gates 2 Nos |
|
| Constt: of carparking shed |
|
| constt: Int: roads |
|
| Ext: E.I etc. |
|
| Cost of Land |
Paid Rs. 1.2 (M) cost of land. |
|